Dear All

If a dam is designed for 50 years flood and 100 years flood reached the dam and passed through the spillway, I used reservoir routing to rout such flood. I found the method does not account for the dam capacity in the routing procedure does any of you faced such problem? The method accounts only for the surcharge storage above the crest. However, the dam capacity is not considered in the equations. Any of you have explanation about that. 

In my opinion,( the volume of the outflow-the volume of inflow) should be equal to (the surcharge volume + dam capacity) . But this is not fulfilled. Any clue for this is appreciated. 