I'm verifying a field embankment supported by ESC monitoring data using plaxis 3D and i'm trying to reach the field values using the available data from soil tests performed, yet the excess pore pressure is still above recorded, any tips to minimize it ?
P.S: I tried changing Kv, Kh but the available measured values don't fit unless i increased it x10, is it normal?