I am modelling Reinforced concrete frame using TNO Diana. I have used Concrete model as total cracked fixed with tension curve as exponential and compression curve as thorenfeldt. it requires E, poison ratio, density, fc', ft, Fracture Energy and shear retention factor.
For steel I used Von-mises model which requires E and fy.
When I apply cyclic loading the peak load from the FEM software around 35KN on one side but on other side it is about 60KN. Does anyone have any idea why this is happening? Please see the attached picture showing experimental and software result.
Thankyou