NERC Disturbance Control Standard specifies that regulating and supplemental reserves must be able to reach their full capacity within 10 minutes, but since capacities may differ dramatically, this definition will not describe the feasible MW increase within a minute. For instance, a 50 MW unit that meets the aforementioned standard will have a ramp rate of at least 50/10 = 5 MW/min, but a 500 MW will have a ramp rate of at least 50 MW/min. We cannot consider 5 MW/min to be as good as 50 MW/min!