28 December 2017 3 5K Report

1. The HRSG is vertical and has 13 heat exchangers.

2. The Problem I am facing are as follows:

a. The control logics for Aspen Dynamics (I have put the controllers for levels of three drums by manipulating input to the drums

Finally, I want the help on :

1. Inputs to other control logics involved in a typical HRSG

2. Simulation on startup/ shutdown of a typical HRSG.

the help will be appreciated.