1. The HRSG is vertical and has 13 heat exchangers.
2. The Problem I am facing are as follows:
a. The control logics for Aspen Dynamics (I have put the controllers for levels of three drums by manipulating input to the drums
Finally, I want the help on :
1. Inputs to other control logics involved in a typical HRSG
2. Simulation on startup/ shutdown of a typical HRSG.
the help will be appreciated.
thanks