Hello,
I have the model setup with 3 nested domains with inner grid size of 700x700 with 5 km resolution. Other domains are in the multiples of 3. I have to estimate the Model processing and storage requirement for 3 days of forecast in 3 hr interval with GFS 0.5 deg data set. The other model configuration is listed below.
#Domain
Time_step = 75 sec
e_vert = 30
#Phyics
sf_ocean_physics = 0
chem_opt = 0
mp_physics = 3, WSM 3-class simple ice scheme
ra_lw_physics = 1, rrtm scheme
ra_sw_physics = 1, Dudhia scheme
radt = 50 min
sf_sfcaly_physics = 1, MM5 Monin-Obukhov scheme
sf_surface_physics = 2, Unified Noah land-surface model
sf_urban_physics = 0, activate urban canopy model
bl_pbl_physics = 1, YSU scheme
bldt = 0
cu_physics = 1, Kain-Fritsch scheme
isfflx =1
ifsnow = 0
icloud = 1
#dynamics
rk_ord = 3