I am simulating the system 6 nodes Billiton by sequential monte carlo simulation and the results obtained do not match the literature. I need guidance because I have reviewed the code on several occasions and cannot find the error.
For example'm modeling Billiton 6-node system for maximum demand and LOLE in the literature is around 73 hours a year. With the simulation of non-sequential monte carlo agree with the outcome, but with sequential monte carlo simulation result I get is 55 hours per year. The simulation is performed in the matlab and can not find the problem.