As per literature, SRT is estimated according to the equation

SRT = Xr*Vr*tc / (Xw*Vw+ Xe*Ve)

Xr=VSS content in the reactor (mg/L), Vr= working volume of the reactor (L), tc = cycle length (d), Xw= VSS content in the sludge wasted (mg/L), Vw= volume of sludge wasted (L), Xe = VSS content in effluent discharged (mg/L), Ve volume of effluent wasted.

There is no settling phase, Ve=0. The Vw amount of mixed sludge is removed at the end of cycle without any settling phase. Would the SRT change or remain the same.? What would be the SRT of the SBR?. Can we consider SRT=HRT?