The difference between HMA and WMA:
Different authorities have defined different temperature ranges for these two types of mixtures. Based on the Illinois Asphalt Pavement Association Scholarship:
* A batch of HMA consists of aggregate and a viscous binding agent and is produced at a temperature range of about 300-350 ° F (149-177 °C).
** A batch of WMA is produced at a temperature range of 50-100 ° F (10-38°C) less than a batch of HMA.
Laboratory Procedural Differences:
HMA is typically produced between 275-350 ° F (135- 177°C); while WMA can be produced 100 degrees lower (38°C).
The HMA mixture should be poured at a specific temperature (greater than 10°C). The WMA mixture is sensitive to temperature changes because they are produced at a lower temperature. Are there special temperature conditions for WMA mixes that have a lower temperature range?