How to simultaneously maximize project triple constraints at the same time i.e. complete a project in the shortest timeline, the lowest cost (including risk) & the best quality?
How to harness the best optimized resources i.e. people, process, tools / technologies & raw materials etc. to improve project performance / project success?
How to leverage big data analytics & IoT to improve project performance / project success?
Total clarity of scope of work, variations in duration of activities while working, variation in technology, availability of resources , availability of funds at right time, dynamic nature of project requirements. Many of the above factors offers challenges for Project Management.
What are some of the gaps in project management?- Above reasons mentioned by the scholars are the important causes. Beside these, I think lack of resource person and another one appropriate funding with right brain in right project. Regards Ajit Kumar Roy.
Uniqueness of each project, most of the activities being done first time, large investment, novelty of project, complexity of project may lead to gaps.
Inconsistency among practitioners in the same organization; some participants seems to be doing more than others in practicing/applying project risk management … and some have better understanding of the project risk management processes than others.
Some do a good job in utilizing project risk management on larger projects but do not do it (or properly perform project risk management activities) on smaller projects.
Not sure if “all” recognize the value of project risk management and if they do – are they willing to put the necessary effort that is appropriate to the value? In other words, do we have a gap between what we say and what we do?
Workload does not allow the project managers enough time to perform proper risk assessments and management.
It is difficult to gather all stakeholders for risk management activities. Further, technical stakeholders do not give proper value to project risk management.
Training & Development Gaps
Some feel that they are practicing project and risk management in an “Ad Hoc” or accidental way and they were not properly trained for project management or project risk management (Accidental Project Manager syndrome).
“We have an excellent tool in place”; but some could not answer specific questions about the tool and there is seems to be differences of opinion here.
Planning Gaps
Need to incorporate project risk management and other project management activities into the overall planning effort (time and other considerations).
Some say “we have good planning” but others says there is a gap, “not fully following all processes”.
Risk Identification Gaps
It is common that team members limit risk identification to obvious project risks and they conduct the identification exercise in a brainstorming mode staying on the high level. They are not including other tools and techniques, including drilling down into a work breakdown structure (WBS).
“Usually we identify a few risks on a project but sometime we could have a large number of risks.”
It is important to have the right balance between quantity and quality of risks identified. The objective is not to identify hundreds of meaningless risks, rather to identify as many risks as possible in order to effectively manage the project and its risks.
Lack of proper follow-up during execution … “We do a good job in planning but when we go into execution …”
There is no real enforcement for the project managers to do risk management and follow-up … so most projects still do the risk assessment but not the full “management” or follow-up.
Organizational System Gaps
It is important to have a knowledge management system in place that includes lessons learned.
The knowledge management system should be user-friendly and allows retrieving lessons learned readily.
It also appears that there is no “standard” way for scoring risks; basically how to assign a 1, 2, or 3 to the risk probability or impact. Therefore, risk ranking is left to each team preferences.
Availability (lack of) lessons learned on previous projects (especially for new type of projects). In addition to lack of experience on new type of projects (new services).
There are differences between contingency reserve and management reserve but this is not clear within many of the organizations we work with and/or the concept is not fully utilized.
It is not easy to reach a common view among stakeholders; no alignment. This may seem a people issue but the root cause is system issue and related to lack of standard way for scoring risks.
Miscellaneous Gaps
Fighting fires, which might be a symptom of not doing enough risk identification and proactive management …
In a client organization, project managers are quantifying even the medium and low priority risks, which might be acceptable but this is not a “preferred practice” and is an extra effort that might not be justified by the benefit.
There should be a project classification system (typically 2, 3, or 4 project classes). If such a classification system exists it should be used for all project management functions; including risk management.
In some cases, “we start early without contract”; this practice is leading to ambiguity of scope, which increase uncertainty, and obviously increasing risk.
There are difficulties related to cultural and governmental issues in other countries or even in remote, rural areas.
Decision Theory Gap
In this section we present a brief review of those essential elements of the info-gap decision theory, which are employed in the subsequent example. Further details are to be found in Ben-Haim (2006). Info-gap theory provides two decision functions: the robustness function enables the planner to maximize the immunity to failure, while the opportuneness function enables the optimal exploitation of favorable circumstances.
Models of Uncertainty Gap
Our quantification of uncertainty is based on non-probabilistic info-gap models. The intuition underlying info-gap theory is the idea that uncertainty is a disparity between what the decision-maker knows and what could be known. Info-gap theory is particularly suited to situations of severe lack of information. For instance, an info-gap arises when available information is exhausted in constructing a “best model” in which fidelity to reality is unreliable or unknown. An info-gap refers to that unstructured realm, beyond our current knowledge, within which lie emergent possibilities. Info-gap models are not needed, and probability theory should be used instead, when experience or understanding are sufficient to characterize the likelihood or systematics of recurrence.