Dear all,
I have calibrated and validated the baseline scenario. Now I want to develop another scenario with new land use map base on calibrated scenario. so I have the following questions:
1-should I start a new swat project and upload all data again and set parameters with the calibrated parameters?
or
2-can I copy the calibarted baseline and do as follows:
-copying the previous calibrated baseline scenarios
-noting to do with watershed delination
-uploading new land use map
-nothing to do with soil and slop map (they are the same as before; should we upload them again?)
-overlaying again
-doing HRU definition
-nothing to do with weather data (should we upload them agin?)
-again creation of input
-rewrite the input data (land use data)
-run again
-read out put again
-finish
Thanks for the responses and regards,
Shima