I want to bind a classical project scheduling problem with Cmax objective function. For example, the first and the second activity can start at the beginning of the project. I want to limit the model in which 1st and 2nd activities never run at the same time. But I don’t know which one is scheduled earlier. Moreover, in my model, just these two activities use the same resource. This resource is bounded, hence model is a special case of RCPSP. How can I handle the resource constraint on my model?