it is as following :

A capacitated lot sizing problem with :

-multi item

-multi machine

-minimum inventory constraints

-changeover times between items

-It's a big bucket problem, the horizon is 18 months and periods are months

Can you please give me insights about how to solve it ( without any solver only oriented programming ), knowing that it is NP hard and I have very large instances with 18 periods, up to 5000 items and 20 machines.

Thank you very much