Hi everyone,

I’m using FullProf to perform Rietveld analysis on Portland cement pastes. I’m a beginner with this technique. My χ², Rp and Rwp seem to stall around χ² ≈ 1.46, Rp = 14.6%, and Rwp = 19.0%. I’ve tried multiple refinement attempts, but the fitting doesn’t improve.

Questions:

  • Are these Rp/Rwp/χ² values reasonable for cement pastes?
  • What would you check first to improve the fit in such systems? (e.g., background function, peak asymmetry...)
  • Do you have typical ranges for Rp/Rwp that you consider acceptable for well-modeled cement paste datasets?

Regards,