08 August 2016 3 8K Report

I am simulating push-out analysis in Abaqus dynamic explicit in which I want to use restart analysis since there are many steps involved. I have a problem with restarting the job. After editing the model attributes, I want to continue the job from a specific step. Therefore I edited the Attribute and set the step and odb file to restart the job. However, after submitting the job, I got this error:

"A NODE SET WITH THE SAME NAME "ASSEMBLY_Concrete Slab-1_SET-1" DEFINED IN THE ORIGINAL ANALYSIS HAS BEEN REDEFINED IN THE CURRENT ANALYSIS. EXISTING SETS CANNOT BE MODIFIED IN A RESTART ANALYSIS."

I checked the whole model but I couldn´t find any mistake in the model (as

mentioned in the error such node sets with the same name). I was wondering

could anyone give me a hint that what can be the reason?