Hi everyone,

I am a Ph.D. student and I am working on the production scheduling of an open-pit mine by genetic algorithm, and I have a problem with converting infeasible sequencing to a feasible one, so I need someone to help me. how can I create a normalized plan based on a completely random solution? on the other hand, how can I change the time periods that are assigned to genes of the chromosomes or all blocks of the ultimate pit?

I don't know any normalization method for obtaining a feasible sequencing plan, and I studied some papers related to it, but the normalization methods the authors used, have not been stated in detail! because when it is assigned a time period to blocks, there is any rule to regard the condition of 45 degrees on slopes!!!

I want to explain more about the MATLAB code I wrote. Precedence constraints (These constraints ensure that a block can only be extracted during some time period t if all of its predecessor blocks have been mined completely before or during time period t) are not true, I think because when I import the results into Surpac software, the extraction of blocks and sequencing of them seems like strip mining regardless of 45 degrees on slopes and instead of formation of inverse cones! I don't know how can I implement the normalization process you mentioned above?!

I attach an output file of MATLAB so you can see.

Thank you in advance

More Elham Lotfi's questions See All
Similar questions and discussions