Dear all,

I am modelling a secant pile wall in Plaxis 2D. Pile length is 24m and embedment depth is 7m. I am modelling a staged construction. I have a strut at the top (nearly 1 m below the ground). Even though I excavate 1.7m depth of the soil, toe of the pile starts moving. Do you know how can I deal with this issue? Thank you very much in advance.