Hi All,
I am working on the rehabilitation of a fire-damaged structure.
Should I consider the Column below Soil structurally deficient.
visually it doesn't look like fire affected the column below grade.
Should I retrofit whole member or just the section above plinth beam.
as Slab on Grade is a 6" the Plain Concrete Slab which is difficult to chissel/excavate.