I asking about the logic behind sizing of transformers connected to solar inverters in utility scale solar PV plants because actually we say all of manufacturers, consultants and EPCs approve sizing 2 MVA transformer to 2 MW inverter and what actually happens that after energizing the plant transformer just give you lots of problems like over temp. trips and even winding fail or burn and this actually what happened with us in two transformers failed just after energization by 1 month

Anyone have calrification ?