Hi All
How exactly is the air or wet cooled condenser sized and controlled in a power plant?
For example, for a wet cooled condenser, is the design/nominal exhaust turbine pressure calculated based on the 1- max wet bulb temperature experienced onsite 2- average wet bulb temperature 3- or average max?
Also, while the plant is operating, say one day the wet bulb temperature was higher than the design value, do plant operators simply increase the cooling water flow rate to ensure the exhaust pressure is fixed or let the turbine exhaust pressure increase which would slightly hurt its power generation?
In other words, do we size and/or control the condenser such that the turbine exhaust pressure is fixed or the exhaust pressure is allowed to float based on weather conditions?
Thank you all