I am trying to model early-age concrete temperature modelling in ABAQUS. The issue I have here is after 24 hrs, the formwork is removed and after a gap of 1 hr, insulation is added in place of the formwork. I am able to model the procedure in ABAQUS till the part where the concrete formwork is removed. However i do not know how to add insulation in ABAQUS, since it occupies the same position as the formwork (the formwork is replaced by insulation). Does anyone have an answer/suggestion for the same?