Motors frequently need to be operated under varying load conditions due to process requirements. Mostly a motor is selected based on the highest anticipated load. But the highest load can occur only for a short period of time. Instead a motor can be selected with a rating slightly lower than the peak anticipated load which can operate at overload for a short period of time. Example: For a particular load cycle, the average load is around 69kW with peak load(180kW) occurring for a few seconds. For this load cycle, it won't be cost efficient if we select a motor with rated power around 180kW. What is the appropriate way to select a proper sized motor that would operate at its highest efficiency for maximum time?