I currently have an activated sludge (AS) waste water treatment plant (WWTP) on site, and I want to decrease the retention time for the treatment process while improving the results from the plant.
I am currently designing a disinfection chamber with UV to improve the results, and considering a tertiary filter. But I still need to reduce the retention time because the plant is under-capacity.
Is it logical to install another tank for MBBR treatment after the clarifiers and before the blending tank? Or should I utilize the biological treatment tank and scrap the AS all together?