We have set up a test field for highway stormwater monitoring on Rijeka city bypass as a start of our stormwater monitoring program. ADT on this bypass is between 15000 and 50000. We are in the process of creating our monitoring plan and I would appreciate if anyone could share their experiences in sampling, sample volume and which elements should be included in analysis.

Our test field is on an intersection with a closed, watertight drainage system and there are 3 small watersheds from which stormwater goes to an oil and grit separator. we plan to take samples form 5 locations - 1 from each watershed, 1 before and 1 after the separator.