4 Questions 21 Answers 0 Followers
Questions related from Zoran Berisavljevic
Above-mentioned authors derived an equation for determination of rock mass modulus based on back-analyses (among other investigations) of tunnel excavations. Does this mean that Erm is unloading...
15 December 2021 5,021 3 View
Hi, The required material for the construction of one motorway embankment is csa 0-300mm? Fines percent limit is set at 10% max. The uniformity coefficient required is cu>9. Large diameter...
12 December 2018 3,372 2 View
Hello, Does anybody have experience with negative effects of freeze/thaw cycles on crack occurrence in asphalt due to ice lens formation in crushed stone aggregate with considerable fines content...
22 July 2018 2,129 2 View
I need explanation regarding tieback bolt implementation and interpretation in Phase2, when analyzing deep excavations in rock. 1. What are suggested values of residual tensile capacity and bond...
18 May 2017 5,359 0 View