I’m seeking reliable data on the typical construction timeline for setting up a processing plant, specifically for industrial/construction minerals and metallic ores. Below is a breakdown I’ve encountered, but I would appreciate feedback or references to studies or reports that validate or refine these estimates:

  • Site preparation: 4-8 months
  • Civil works: 12-18 months
  • Installation of equipment: 8-12 months
  • Finishing work: 3-6 months

i.e 24 - 48 months on average.

Are these timelines consistent with industry standards, and could anyone provide more detailed insights or case studies related to such projects? Any references to credible sources or personal experiences with processing plant construction would be very helpful.

Thank you!