Thin slabs require additional reinforcement at the slab-column connection in the form of stud rails to resist punching shear and prevent column from punching the slab.
In our project we are keeping stud rail in the railway truss top which will be connected PC Roadway span. In those PC roadway span we keep some hole where the stud rail can take place with some covering area. afterward concreting will be performed at those hole.