design of abutment.
At-rest soil pressure is developed during the construction of bridge
abutment. Active soil pressure are developed when the abutment are
pushed forward by backfilled soils at the back of abutment wall. A state of
equilibrium shall be reached when the at-rest pressure is reduced to active
earth pressure. Hence, at-rest pressure is considered when assessing the
stability of abutment while active pressure is adopted when assessing the
adequacy of structural elements of abutment.
Passive pressure is only considered in integral abutment which
experiences passive pressure when the deck expands under thermal other
effects.
Passive pressures are developed when the abutment wall pushes the soils
at the front of abutment. Given that larger movements is required to
mobilize passive pressure than active pressure and the abutment is
designed not to slide under active pressure, it is normally assumed that
passive pressure does not develop at the front of abutment. Moreover,
there is a possibility that soils may be removed temporarily owing to utility
diversion; it is normally assumed that stability contribution by soils in front
of abutment is ignored.
Thanks Dr Amkad for brief answer
https://www.youtube.com/watch?v=WLEkC_JbTsQ
03 April 2017 1,301 2 View
How we can design box girder bridge?
02 March 2017 10,163 3 View
Why 0.2 mm crack width?
02 March 2017 9,354 3 View
How does rust affect on the bonding between steel bars and concret?
02 March 2017 3,458 10 View
In normal concrete structures, 28-day test results are often adopted.However, in the construction of high-rise buildings using “High strengthconcrete”, compressive strengths based on 56 or 91-day...
02 March 2017 8,839 19 View
What about difference between those approaches regarding load and material safety factor?
02 March 2017 587 2 View
Relation between cubes and cylinder
02 March 2017 5,836 4 View
Non destructive tests
02 March 2017 5,452 31 View
Can we use same code provisions of columns for piles?
02 March 2017 7,906 3 View
Assume that there is no differential settlement.
02 March 2017 7,651 3 View
Hello everyone, I recently submitted an article to Geotechnical Engineering (Proceedings of the ICE), and the current status has been listed as "EiC Pre-assessment: Ready" for the past 20 days. I...
10 August 2024 6,493 1 View
Hello experts, Does anyone know any free software about retention index prediction ?
08 August 2024 7,403 2 View
Molecular docking software/ websites?
02 August 2024 8,704 7 View
What should a Mechanical Engineering PhD scholar focus on during their PhD to enhance their chances of securing a postdoctoral position?
29 July 2024 7,714 4 View
In some data sources it has been grouped in Q1 and some shows it is Q2.
29 July 2024 4,227 2 View
I created a file with my outgroup and ingroup species using Beauti, ran it in BEAST, viewed it in Tracer, and then used TreeAnnotator to create a file that I imported into RASP. Could someone...
28 July 2024 2,979 1 View
Your comments
28 July 2024 2,822 2 View
Dear Research Community I would like to invite Elctrical Engineering specialists to solve problems related to Ternary Algebra or tripple sets I have an algorithm that places in relation three...
28 July 2024 5,771 2 View
Contemporary scores or innovations in scientific approaches. Hybrid methodologies, emerging themes and cross-cutting issues?
27 July 2024 648 3 View
Novel areas especially
24 July 2024 8,416 0 View