05 May 2016 6 5K Report

In unbonded post tension concrete flat plate slab - Multi story building, in case MEP installation were a drill used in concrete slab make a penetration in bottom more than 3/4" (the min concrete cover for PT cable) and then cut the cable, it can been seen goes out side edge slab around 3" , but the question is: if curtain wall used as facade, all edge slab will be hidden, how can I know if we have a new cut cable?

the picture shows one PT (Post tension) cable hit (drill cut it under the slab) in the middle of floor, you can see how its easy to note it, 