Please help me to understand which failure on a production line should be prioritized when comparing failure 1 which occurred 5 times in the month and consumed 10 hours (total) versus failure 2 which occurred 10 times but consumed 5 hours (total). What index (or calculation) can I use to know which failure to prioritize for improvement efforts?