Geopolymer concrete- an alkali activated flyash + slag blended concrete gives early strength with moist curing at ambient temeprature ( 25 degree C) in our study. But it is workable only for a period of 30-40mts and hence there is a limitation in using in in-situ concrete. Is there any way to improve its workability to minimum 2hours and the final placing slump shall not be less than 120mm.