Hi, I am working on PV system grid integration, for connecting the PV ssytem to teh grid through DSP, how to synchonize. I am using the TMS3200f28835 DSP kit, we are taking the grid voltage as a reference for syncronization
You should should measure the grid voltage (point of common coupling) using voltage sensors. Then, you should design a phase locked loop (PLL) to obtain the grid voltage angle.Using this angle you can apply the voltage oriented control and achieve the synchronization with the grid.
You should should measure the grid voltage (point of common coupling) using voltage sensors. Then, you should design a phase locked loop (PLL) to obtain the grid voltage angle.Using this angle you can apply the voltage oriented control and achieve the synchronization with the grid.